Maža kaina - didelė vertė. Prenumerata vos nuo 1,00 Eur!
Išbandyti
2013 07 15

Contractors struggle to meet their obligations at Klaipėda port

Millions of litas in private and public funds being spent on building quays in Klaipėda and deepening the port's waters are no guarantee that the contracted work will be done successfully, the daily Lietuvos Žinios reports.
Klaipėda
Klaipėda / Aurelijos Kripaitės/15min.lt nuotr.

Contractors receive more criticism than praise from Roma Museckienė, the port's infrastructure director.

Hidrostatyba, which is building Kairių Street leading to the port's ferry terminal together with its partner Lemminkainen, in an exception. Under a contract worth 33.8 million litas (EUR 9.7m), the work is to be completed in March 2014, but the rapid speed at which the street is being built suggests that most of it will be ready for use this year, the director believes.

Klaipėdos Smeltė's quays unexpectedly became one of the most difficult stretches of the port.

While Germany's Josef Mobius and Lokys, a now-bankrupt Lithuanian company, were buildings quays 82 to 89, the stevedoring company's shareholders changed and so did the purpose of the quays. There were lengthy arguments about who would modify the project and who would pay for that.

After Klaipėdos Hidrotechnika and Josef Mobius won a contract for new quays, numbers 90 to 96, it was expected that the work would go much more smoothly.

As part of its plans to handle containers at Klaipėdos Smeltė, the company's owner, Terminal Investment Limited (TIL), earmarked 100 million litas for investments in cranes and other equipment. However, this business plan fell through because of disagreements between the contractors and the port's authority. The cranes have been delivered, but the quays have not been built yet.

Report mistake

Successfully sent

Thank you

Economy

Lithuanian producers of EPS on the way to circular economy
Gilužio Rivjera by the real estate company Homa – hundreds of apartments and millions in investment
Capitalica fund successfully issued bonds amounting to EUR 5 million to finance the Verde project in Riga

Feature

State Progress Strategy 'Lithuania 2050': will Lithuania become the 'Silicon Valley' of social enterprise?
Citus Experts: Planning to Furbish or Brush Up your Home Interior? Get Ready for a Brutal Run
How do the country's most desirable employers nurture IT talents?

Opinion

Ramūnas Vilpišauskas. The president’s achievements in Brussels were modest
Laurynas Jonavičius. Will the new German government’s foreign policy coincide with Lithuanian interests?
Eastern Partnership ‘beyond westlessness’: a new momentum for the European integration

Politics

Taiwanese Minister Ming-hsin Kung – about Lithuania’s strengths and the two countries’ looming plans
The double standards of “values-based policy”: Lithuania did not join the condemnation of Turkey
Behind the scenes of ambassadorial appointments: Seimas looking for clarification on continuing questioning at the Presidential Palace
Užsisakykite 15min naujienlaiškius